This project includes $2 million of roadway improvements south of Marshall for a smoother and quieter ride. Sections of the concrete roadway will be repaired in two locations south of Marshall. This virtual open house provides an overview of the project and information on detours that will take place during construction.
About this Virtual Open House
The entire session should take no more than 15 minutes to complete. Continue clicking through to learn more about the project and what to expect during construction.
Following guidance from state health officials to prevent the further spread of COVID-19, the Minnesota Department of Transportation has temporarily postponed all public meetings and in-person events. Public engagement on transportation and construction projects remains a priority, and we appreciate you joining us online to learn more about this project.
How to navigate:
Click the arrows on the bottom right of your screen to go forward or the left to go backward. Use the navigation bar on the left of your screen to revisit any part of the meeting. Click through all five slides to learn more about the next steps of the resurfacing project.
How to participate:
This meeting is now closed. To contact the MnDOT project team please visit the project webpage: www.dot.state.mn.us/d8/projects/hwy59marshall
Project Overview
In summer 2021, MnDOT is planning to repair sections of the concrete on Highway 59 in two locations south of Marshall:
- Highway 59 from the intersection of Highway 23 in Marshall to the intersection of County Road 6 (south of Marshall).
- Highway 59 from the intersection of Highway 14 (near Garvin) to just north of the intersection of Highway 30.
Project Locations
Click the image above to enlarge.
Project Process and Benefits
The concrete repair will involve completely removing sections of the roadway and then replacing those areas with new concrete. In addition, the roadway will also receive diamond grinding. Diamond grinding is a process that removes a thin layer from the surface of the roadway to get rid of imperfections caused by construction.
The improved Highway 59 roadway will have a smoother surface and will offer a quieter ride.
Project Schedule
Please note that time frames are all approximate, subject to change and weather and schedule permitting.
What to Expect During Construction
Construction Impacts
Our project team will be available to businesses, residents and visitors before, during and after construction. We’ll continue to listen to your needs and concerns and make adjustments when possible.
Overall construction impacts:
|
|
Traffic impacts:
|
|
Pavement impacts:
|
|
Area access:
|
|
Planning and Navigation:
|
|
Example Construction Photos
Stay Informed
Watch for message boards in the area with real time directional information.
Click to the next slide to learn more about detours and traffic impacts during construction.
Detours and Traffic Impacts
Highway 59 between Highway 14 and Highway 30
- Planned dates: Mid-July through Mid-September
- Full closure of Highway 59 in this area
- Detour uses Highway 14, Highway 5, Highway 29 and Highway 12 to get around the closure
- Lake Shetek will be accessed using County Highway 48
- All businesses and residences will remain accessible during the project
Highway 59 between Highway 23 and County Road 6
- Planned dates: Mid-September through Mid-October; construction on this section may occur sooner
- Full closure of Highway 59 in this area
- Detour uses Highway 23, Highway 35 and Highway 6 to get around the closure
- Local access only for residents who live in the construction area
- All businesses and residences will remain accessible during the project
Stay Connected
Thank you for your interest in the Hwy 59 Concrete Repair Project.
Submit a Question
This meeting is now closed. To contact the MnDOT project team please visit the project webpage: www.dot.state.mn.us/d8/projects/hwy59marshall
Sign Up
For more information about the project and to sign up to receive email updates, please visit: www.dot.state.mn.us/d8/projects/hwy59marshall
Connect
Join the Facebook group: MnDOT | Southwest Minnesota Facebook Group
Share
It is important for the community to understand what to expect during construction. Please pass along the link to this virtual open house to your family, friends and coworkers that use Highway 59 in this area so they know what to expect and can sign up for email updates.
Contact the Project Team
Cody Brand
MnDOT Project Manager, District 8
320-979-4720
cody.brand@state.mn.us
Mandi Lighthizer-Schmidt
MnDOT Director of Public Engagement, District 8
320-214-6426
mandi.lighthizer-schmidt@state.mn.us
Plan Ahead
For real-time traffic and travel information in Minnesota, visit www.511mn.org or get the free Minnesota 511 smartphone app from Google Play or the App Store.